  1. 01

    Place the ground connections

    First action on the slab — anchor the two ground connections, mark W × P footprint.

    FRAME
    25 min
  2. 02

    Insert the pillars into the ground connections

    Insert the front PN-VP-100 pillars onto ground connections — plumb in two directions.

    FRAME
    18 min
  3. 03

    Fix the wall profile to the wall

    Anchor PN-WP-100 wall profile at H1 / H2 height — laser-level the entire wall line.

    FRAME
    25 min
  4. 04

    Install the front gutter profile

    Install the front PN-GU-300 gutter profile between pillars — finger-tight first.

    FRAME
    22 min
  5. 05

    Install drain tubes and drainers

    Install drain tubes (PN-DT-100) and PN-WD-100 water drainers in the gutter.

    FRAME
    12 min
  6. 06

    Prepare carrier fixing nuts

    Pre-load PN-NT-080 channel nuts into all carrier-fixing positions.

    FRAME
    12 min
  7. 07

    Insert the main carrier profiles

    Insert main carrier profiles (PN-MC-100, PN-MC-110 mid-span) front to wall.

    CARRIERS
    30 min
  8. 08

    Fix main carriers with brackets

    Fix main carriers with PN-BR-300 brackets at both ends — bracket alignment critical.

    CARRIERS
    25 min
  9. 09

    Insert cover profiles between carriers

    Insert PN-CP-300 cover profiles between carriers — defines glass/polycarbon channels.

    CARRIERS
    25 min
  10. 10

    Insert glass or polycarbonate infill sheets

    Drop in PN-GL-300 glass or PN-PC-310 polycarbonate infill panels — handle with cups.

    CARRIERS
    38 min
  11. 11

    Install main carrier covers and seals

    Install main carrier covers and PN-GS-300 / PN-PC-300 seals — seals match infill type.

    CARRIERS
    30 min
  12. 12

    Install optional gutter extension profile

    Install optional PN-GE-300 gutter extension profile if specified.

    FINISH
    18 min
  13. 13

    Install gutter and wall profile end covers

    Install gutter and wall profile end covers (PN-EC-300) — clean visual close-out.

    FINISH
    12 min
  14. 14

    Seal the wall joint and complete the system

    Apply PN-SL-100 silicone at the wall joint and complete the system handover.

    FINISH
    18 min

About this wall-mounted glass / polycarbonate veranda installation guide

Luxa Vetra — Wall-mounted glass / polycarbonate veranda · LuxaShade aluminium roof family. 14 steps · 2 installers · Edition 2026.1.

EN AW-6063 T6 alloy · QUALICOAT class 2 powder coating · EN 1991-1-4 wind-load rated · RTS-compatible motor wiring on motorised variants.

Why follow the official PONARC × LuxaShade procedure

  • EN 1991-1-4 · QUALICOAT class 2 · EN AW-6063 T6
  • RTS-compatible motor wiring (motorised variants)
  • Gutter slope 1.5% · drainage inside columns
  • Edition 2026.1 · January 2026 · EN

Other guides in this library

EN 1991-1-4 · QUALICOAT class 2 · EN AW-6063 T6 · RTS · M10 Buldex · IMBUS

PONARC Engineering Reference · Edition 2026.1 · January 2026 · EN