INSTALLATION GUIDE

16 steps to a finished wall-mounted manual bioclimatic pergola.

Wall-mounted aluminium bioclimatic pergola with manual handle operation — wall ledger (PN-WM-500) replaces the rear free-standing frame, two front pillars only. Three perimeter sizes from one shared 16-step procedure.

TOTAL TIME
4h 52min
summed across all 16 steps
CREW
2 installers
recommended throughout
DIFFICULTY
★★★☆☆
moderate · power tools required
EDITION
2026.1
January 2026 · EN
AVAILABLE SIZES Same 16-step procedure across all perimeters · diagonal checks per size
3×3 m
⌐ diag 386 cm
3×4 m
⌐ diag 466 cm
3×5 m
⌐ diag 554.5 cm
  1. 01

    Locate and mark the wall ledger line

    Mark the wall ledger line — the entire roof reference for a wall-mount install.

    FRAME
    15 min
  2. 02

    Anchor the wall ledger (PN-WM-500)

    Anchor PN-WM-500 wall ledger — replaces the rear free-standing frame.

    FRAME
    25 min
  3. 03

    Place the two front foot plates

    Place the two front PN-FP-500 foot plates parallel to the wall ledger.

    FRAME
    18 min
  4. 04

    Lift the two front pillars

    Lift the two front PN-DZ-500 pillars onto their foot plate studs.

    FRAME
    22 min
  5. 05

    Install front carrier gutter

    Install the front PN-GU-500 carrier gutter — match height to wall ledger ±2 mm.

    FRAME
    18 min
  6. 06

    Install side gutters (front to wall)

    Install left and right side gutters — wall-side ends fix to PN-WM-500 ledger.

    FRAME
    22 min
  7. 07

    Seal corner joints

    Apply neutral-cure silicone bead at all four upper corner joints.

    FRAME
    12 min
  8. 08

    Install blade rails (PN-RA-500)

    Slide PN-RA-500 blade rails into the frame channels — pre-set pivot positions.

    BLADES
    18 min
  9. 09

    Prepare lamellas

    Prepare the louvre blades (PN-LM-500 opening + PN-LM-501 fixed reference).

    BLADES
    18 min
  10. 10

    Install the fixed lamella (PN-LM-501)

    Install the PN-LM-501 fixed lamella against the wall ledger — closed-position reference.

    BLADES
    15 min
  11. 11

    Install opening lamellas (PN-LM-500)

    Install the PN-LM-500 opening lamellas (back/wall side first) — equal pitch.

    BLADES
    25 min
  12. 12

    Connect manual linkage

    Connect the manual synchronization linkage — all opening blades move together.

    BLADES
    18 min
  13. 13

    Install manual handle (PN-HD-500)

    Install the PN-HD-500 manual handle — front-side rail, smooth crank cycle.

    BLADES
    18 min
  14. 14

    Set open / close limits and install covers

    Set open / close end-stops and install front pillar caps + gutter closing profiles.

    FINISH
    18 min
  15. 15

    Install drainage outlets and final test

    Connect drainage outlets in front pillars and complete final functional test.

    FINISH
    18 min
  16. 16

    Clean and hand over

    Clean, demonstrate manual operation to customer, hand over warranty card.

    FINISH
    12 min

About this wall-mounted manual bioclimatic pergola installation guide

Luxa Sereno 500M Wall — Wall-mounted manual bioclimatic pergola · LuxaShade aluminium roof family. 16 steps · 2 installers · Edition 2026.1.

EN AW-6063 T6 alloy · QUALICOAT class 2 powder coating · EN 1991-1-4 wind-load rated · RTS-compatible motor wiring on motorised variants.

Why follow the official PONARC × LuxaShade procedure

  • EN 1991-1-4 · QUALICOAT class 2 · EN AW-6063 T6
  • RTS-compatible motor wiring (motorised variants)
  • Gutter slope 1.5% · drainage inside columns
  • Edition 2026.1 · January 2026 · EN