INSTALLATIEHANDLEIDING
26 stappen naar een voltooide Vrijstaande gemotoriseerde pergola.
Vrijstaande aluminium pergola met gemotoriseerd lamellendak — zes omtreksmaten (3×3 → 4×6) uit één gedeelde 26-stappenprocedure.
-
01
Hoekverbindingssets voorbereiden
Pre-build the four corner connection sets — set projection vs width orientation now.
FRAME12 min -
02
Voorste U-frame opbouwen
Insert the front C-1 gutter into B-1/B-2 pillars to form the front U-frame on the ground.
FRAME18 min -
03
Achterste U-frame opbouwen
Repeat for the rear C-2 gutter into A-1/A-2 pillars — keep both U-frames square.
FRAME18 min -
04
De U-vormige frames optillen
Lift both U-frames simultaneously — two installers per frame, mind the powder coating.
FRAME25 min -
05
Linker zijprofiel D-1 monteren
Install the left D-1 side perimeter profile between the two U-frames.
FRAME18 min -
06
Rechter zijprofiel D-2 monteren
Install the right D-2 side perimeter profile — frame is now closed.
FRAME18 min -
07
Diagonalen en afwateringsstoppen controleren
Verify diagonals match the size table (3×3: 386 · 3×4: 466 · 3×5: 554.5 · 4×4: 527.5 · 4×5: 602.4 · 4×6: 683.7 cm) and seat drainage plugs.
FRAME15 min -
08
F-goten in projectierichting monteren
Mount F gutters in the projection direction.
FRAME18 min -
09
E-goten in breedterichting monteren
Mount E gutters in the width direction — perimeter complete.
FRAME18 min -
10
Bovenste goten van bovenaf vastzetten
Fix all top gutters from above with 3.9 mm screws.
FRAME15 min -
11
Rubberen verbindingen afdichten
Seal rubber junctions at all gutter intersections — neutral silicone bead.
FRAME12 min -
12
Standaard lamellen voorbereiden
Pre-cut and prepare the standard PN-LM-500 lamellas to width.
LAMELLEN20 min -
13
Motorlamel voorbereiden
Prepare the dedicated PN-LM-501 motor blade — drive coupling on motor side.
LAMELLEN15 min -
14
Motor op D-1-profiel monteren
Mount the PN-MT-500 motor on the D-1 profile per code map orientation.
LAMELLEN25 min -
15
Motorlamel monteren
Install the motor blade onto the rotation pin first — verifies free movement.
LAMELLEN20 min -
16
Motorarm afstellen
Adjust the motor arm angle so the motor blade closes flush.
LAMELLEN18 min -
17
Resterende lamellen monteren
Insert the remaining standard lamellas one by one — verify rotation by hand.
LAMELLEN30 min -
18
Bewegingsarmen monteren
Install the PN-AR-500 movement arms linking all blades to the motor blade.
LAMELLEN25 min -
19
Bewegingsarm-afdekkingen monteren
Cap with the PN-CV-500 movement-arm cover profiles.
LAMELLEN15 min -
20
Pilaarafdekkingen monteren
Mount the PN-DZ-510 pillar covers (4 corners).
AFWERKING12 min -
21
Achterste afdekprofiel monteren
Install the PN-CV-501 rear cover profile.
AFWERKING12 min -
22
Voorste afdekprofiel monteren
Install the PN-CV-502 front cover profile.
AFWERKING12 min -
23
Hoekafdekkingen monteren
Install the corner cover trims at the four upper corners.
AFWERKING15 min -
24
Motorkabels routen
Route the motor cables down through the designated pillar channel.
AFWERKING15 min -
25
LED-strip en PVC-afdekking monteren
Install the LED strip into the gutter recess and snap on the PVC cover.
AFWERKING18 min -
26
Elektrische bedrading voltooien
Complete electrical wiring at the controller — verify motor direction and end-stops.
AFWERKING30 min
Over deze vrijstaande gemotoriseerde pergola-installatiehandleiding
Luxa Aperio 500 — Vrijstaande gemotoriseerde pergola · LuxaShade aluminium roof family. 26 steps · 2 installers · Edition 2026.1.
EN AW-6063 T6 alloy · QUALICOAT class 2 powder coating · EN 1991-1-4 wind-load rated · RTS-compatible motor wiring on motorised variants.
Waarom de officiële PONARC × LuxaShade-procedure volgen
- EN 1991-1-4 · QUALICOAT class 2 · EN AW-6063 T6
- RTS-compatible motor wiring (motorised variants)
- Gutter slope 1.5% · drainage inside columns
- Edition 2026.1 · Januari 2026 · NL